Rail Baltica to develop next-generation Transport Demand Model

11 March 2021, Rīga – the Rail Baltica joint venture RB Rail AS signed a contract with – TRT Trasporti e Territorio for the implementation of the Rail Baltica Transport Demand Model (hereinafter – DM). The total budget of this contract is 644 000 EUR, and the finalized model is expected by early 2022. The […]

15.03.2021

RB Rail AS signs a contract for hiring temporary professional staff

10 March 2021, Rīga – the joint venture of Rail Baltica RB Rail AS has signed two-year contracts with two companies, Linum Consult Ltd in partnership with Brunel Energy Europe BV and EWI Recruitment, to provide temporary professional staff for the project.  The goal of this contract is to engage professional staff on a temporary […]

10.03.2021

An important step towards implementation of a modern safety standard in Rail Baltica

The international tender for the “Reliability, availability, maintainability and safety (RAMS) consultancy services” has ended and the winner has been selected. The consultancy services will be carried out by inspection, certification and engineering consultancy RINA Consulting. The financial offer from RINA is EUR 510,000.00. The contract was signed on 20th January 2021 and will be […]

04.03.2021

Tender launched for supervision of river Neris bridge construction works

LTG Infra, the company tasked with implementing the Rail Baltica project in Lithuania, has announced a competition for the supervision of construction works for the longest railway bridge in the Baltic States across the Neris river. During the tender, a company will be selected to perform technical supervision of the construction works and will offer […]

29.01.2021

Sandor Liive appointed as Chairperson of the RB Rail AS Supervisory Board

14 January 2021, Rīga – Sandor Liive, a senior management executive and entrepreneur, has been appointed as the Chairperson of RB Rail AS Supervisory Board. He has been a member of the Supervisory Board of RB Rail AS since November 2020. Sandor Liive has replaced Anrī Leimanis, who will continue to serve in the Supervisory […]

14.01.2021

Rail Baltica seeks contractor for building longest railway bridge in the Baltic States

LTG Infra, the company responsible for the implementation of the Rail Baltica project in Lithuania, has launched the second stage of a tender, during which it will select a contractor for the railway bridge over the river Neris near Jonava. This will be the longest railway bridge in the Baltic States, spanning more than 1.5 […]

28.12.2020

Design proposals for section Žeimiai-Šėta will be presented

Spain’s IDOM responsible for the detailed technical design of Rail Baltica section Kaunas-Ramygala will present recommended design proposals in Jonava county on the 21st of December. The section Šėta-Ramygala is 16,5 km long includes 2 railway and 1 road viaducts, 5 animal passages that will ensure that they will be able to safely cross underneath […]

18.12.2020

Rail Baltica project signs 214,3 million EUR Grant Agreements with INEA

Innovation and Networks Executive Agency (INEA) and  joint venture of the Baltic States RB Rail AS on behalf of the Ministry of Economics and Communication of Estonia, the Ministry of Transport of Latvia and the Ministry of Transport and Communication of Lithuania signed two additional cross-border Grant Agreements on the Connecting Europe Facility (CEF) funding […]

09.12.2020

A consortium of Forma 2 and Prointec will supervise the construction of the Rail Baltica station and development of infrastructure at the Riga Airport

A consortium consisting of SIA Forma 2 (Latvia) and Prointec S.A.U. (Spain) has won the open tender for the engineering and construction supervision of Rail Baltica station at the Riga International Airport and related infrastructure. The association has submitted the most economically advantageous tender. Supervision of engineering works will have to be ensured during the […]

08.12.2020

Construction of Rail Baltica viaducts will begin from Rapla County

At a time when one of the largest road viaducts crossing the Rail Baltica railway in Saustinõmme will soon be completed, Rail Baltic Estonia announced the construction procurements for the next objects. “There is a great interest in the construction of various Rail Baltica facilities,” said Tõnu Grünberg, Chairman of the Board of Rail Baltic […]

08.12.2020

RB Rail AS will work remotely

Considering the declared state of emergency in Europe and to prevent the spread of the virus COVID-19, RB Rail AS employees in all three Baltic States currently are mostly working remotely with limited access to the office premises.

30.11.2020