Procurement plan 2025
Below is the information about the indicative Rail Baltica Global Project tenders for 2025 in all three Baltic States. Please note that the material provided is for informational purposes only and is subject to changes or updates during the project's development. For a better understanding, please review the Rail Baltica Global Project governance structure to learn more about the contracting authorities.
Indicative start date
Contracting authority
Status
Procurement title | Short Descritpion of the procurmenet subject | Category | Indicative start date | Contracting authority | Status |
DS1 DPS1A Kaunas (Palemonas)-Šveicarija 0.5-9 km (8.5 km) embankment and structures | DS1 DPS1A Kaunas (Palemonas)-Šveicarija 0.5-9 km (8.5 km) embankment and structures: Installation of a new railway embankment for the double track, construction of engineering structures and roads | Works | 2025 Q1 | LTG Infra | To be announced |
DS1 DPS1B Kaunas (Palemonas)-Šveicarija 9.0-19.4 (10.4) km embankment and structures | DS1 DPS1B Kaunas (Palemonas)-Šveicarija 9.0-19.4 (10.4) km embankment and structures: Installation of a new railway embankment for the double track, construction of engineering structures and roads | Works | 2025 Q1 | LTG Infra | To be announced |
DS2 DPS1 Ramygala-Berčiūnai 78-102.45 (24.5) km embankment and structures | DS2 DPS1 Ramygala-Berčiūnai 78-102.45 (24.5) km embankment and structures: Installation of a new railway embankment for the double track, construction of engineering structures and roads | Works | 2025 Q2 | LTG Infra | To be announced |
DS2 DPS2A Berčūnai-Joniškėlis 102.24-114.8 (12.4) km embankment and structures | DS2 DPS2A Berčūnai-Joniškėlis 102.24-114.8 (12.4) km embankment and structures: Installation of a new railway embankment for the double track, construction of engineering structures and roads | Works | 2025 Q2 | LTG Infra | To be announced |
DPS2-DPS3 Construction of the superstructure of the railway track of the Rail Baltica section Šveicarija-Žeimiai (27.7 km) | DPS2-DPS3 Construction of the superstructure of the railway track of the Rail Baltica section Šveicarija-Žeimiai (27.7 km) | Works | 2025 Q1 | LTG Infra | To be announced |
Design of Point Type Objects (3 bridge structures) | Design of Point Type Objects (3 bridge structures) | Works | 2025 Q1 | LTG Infra | To be announced |
Design and design supervision services of the new railway infrastructure maintenance depot in Panevėžys district | Design and design supervision services of the new railway infrastructure maintenance depot in Panevėžys district | Services | 2025 Q1 | LTG Infra | To be announced |
Design and design supervision services of the new railway infrastructure maintenance depot in Kaunas district | Design and design supervision services of the new railway infrastructure maintenance depot in Kaunas district | Services | 2025 Q1 | LTG Infra | To be announced |
Design and design supervision services for the Rail Baltica railway line between Panevėžys and the LT/LV state border | Design and design supervision services for the Rail Baltica railway line between Panevėžys and the LT/LV state border (114.8-168.6 km) | Services | 2025 Q1 | LTG Infra | To be announced |
Design and design supervision services for the construction of the new railway infrastructure | Design and design supervision services for the construction of the new railway infrastructure (regional passenger stations) | Services | 2025 Q1 | LTG Infra | To be announced |